ANALISYS OF MOST PROBABLE AND EXPECTED TIME OF CONSTRUCTION OF THE PUBLIC BUILDING

Boris Kupčinovac (2015)
Sveučilište Josipa Jurja Strossmayera u Osijeku
Građevinski fakultet Osijek
Zavod za organizaciju, tehnologiju i menadžment
Katedra za organizaciju i tehnologiju građenja
Metadata
TitleANALIZA NAJVJEROJATNIJEG I OČEKIVANOG VREMENA IZGRADNJE JAVNE GRAĐEVINE VISOKOGRADNJE
AuthorBoris Kupčinovac
Mentor(s)Saša Marenjak (thesis advisor)
Abstract
Cilj diplomskog rada je određivanje ukupne duljine najvjerojatnijeg i očekivanog vremena za izgradnju projekta javne građevine visokogradnje prema definiranoj listi aktivnosti i određivanje vjerojatnosti ostvarenja proračuna. Za vjerojatnije vrijeme načinjena je analiza kritičnog puta i histogram angažirane radne snage. U ovom radu je obrađena Osnovna škola locirana u Istri. Za izradu proračuna duljine trajanja projekta su korištene dvije metode, Metoda kritičnog puta (CPM) i Tehnika ocjene i provjere projekta (PERT). CPM metodom se dobiva najvjerojatnije vrijeme završetka projekta, a PERT metodom očekivano vrijeme. Nakon njihovih izračuna, radi se usporedba i određuje se koje je vrijeme vjerojatnije, te se s tim vremenom ulazi u detaljniju analizu.
KeywordsCPM gantt chart histogram PERT
Parallel title (English)ANALISYS OF MOST PROBABLE AND EXPECTED TIME OF CONSTRUCTION OF THE PUBLIC BUILDING
Committee MembersKsenija Čulo (committee chairperson)
Saša Marenjak (committee member)
Hrvoje Krstić (committee member)
GranterSveučilište Josipa Jurja Strossmayera u Osijeku
Građevinski fakultet Osijek
Lower level organizational unitsZavod za organizaciju, tehnologiju i menadžment
Katedra za organizaciju i tehnologiju građenja
PlaceOsijek
StateCroatia
Scientific field, discipline, subdisciplineTECHNICAL SCIENCES
Basic Technical Sciences
Organization of Labor and Production
Study programme typeuniversity
Study levelgraduate
Study programmeUniversity graduate study in civil engineering; specializations in: Hydraulic engineering, Supporting structures, Construction management and technology, Transportation engineering
Study specializationConstruction management and technology
Academic title abbreviationmag.ing.aedif.
Genremaster's thesis
Language Croatian
Defense date2015-09-28
Parallel abstract (English)
The aim of thesis is to determine the total length of the most likely and expected time for the construction project of public building according to the defined list of activities and the probabilities for achieving the estimate. For the most probable duration, the analysis of the critical path and histogram of engaged workforce was made. Thesis was done by using project of primary school located in the Istria, Croatia. For budgeting the duration of the project, two methods were used , Critical path method (CPM) and Program Evaluation and Review Technique (PERT). CPM method gives the most likely time for project completion and PERT method gives the expected time. After calculations were done, the methods were compared and determined which is most likely time, and with that time the more detailed analysis was made.
Parallel keywords (Croatian)CPM gantogram histogram PERT