Integration of biogas power plant rated power 670 kW on e HEP el. network

Toni Luketić (2014)
Sveučilište Josipa Jurja Strossmayera u Osijeku
Fakultet elektrotehnike, računarstva i informacijskih tehnologija Osijek
Zavod za elektroenergetiku
Katedra za elektroenergetske mreže i postrojenja
Metadata
TitleIntegracija bioplinske elektrane snage 670 kW na mrežu HEP-a
AuthorToni Luketić
Mentor(s)Srete Nikolovski (thesis advisor)
Goran Knežević (thesis advisor)
Abstract
Rad obrađuje problem integracije bioplinske elektrane na elektroenergetsku mrežu. Opisan je proces rada cjelokupnog bioplinskog postrojenja s detaljnijim pregledom pogonskih strojeva bioplinskog postrojenja i njihovih principa rada. Ukratko je opisan postupak proizvodnje bioplina, te pozitivni i negativni utjecaji kako proizvodnje, tako i iskorištenja bioplina na okoliš i čovjeka. U radu se nalazi i pregled stanja bioplinskih elektrana u Republici Hrvatskoj. Navedeni su tehnički i zakonodavni uvjeti priključenja elektrane na EEM. U radu je obrađen primjer priključenja Bioplinske elektrane Crnac 1 snage 670 kW na mrežu HEP-a. Izvršena je analiza promatranog sustava pri čemu je korišten programski paket DIgSILENT PowerFactory 14. Analiza pokazuje stanje u promatranoj mreži pri minimalnom i maksimalnom opterećenju i utjecaj kvarova na određenim točkama mreže prije i poslije priključenja elektrane.
Keywordsbiogas power plant gas power plant gas engine CHP biogas biogas plant grid rules study of optimal technical solution of connection of power plant
Parallel title (English)Integration of biogas power plant rated power 670 kW on e HEP el. network
Committee MembersSrete Nikolovski (committee chairperson)
Predrag Marić (committee member)
Goran Knežević (committee member)
GranterSveučilište Josipa Jurja Strossmayera u Osijeku
Fakultet elektrotehnike, računarstva i informacijskih tehnologija Osijek
Lower level organizational unitsZavod za elektroenergetiku
Katedra za elektroenergetske mreže i postrojenja
PlaceOsijek
StateCroatia
Scientific field, discipline, subdisciplineTECHNICAL SCIENCES
Electrical Engineering
Power Engineering
Study programme typeuniversity
Study levelgraduate
Study programmeGraduate University Study Programme in Electrical Engineering; branch: Communications and Informatics, Power Engineering
Study specializationPower Engineering
Academic title abbreviationmag.ing.el.
Genremaster's thesis
Language Croatian
Defense date2014-10-01
Parallel abstract (English)
This paper presents problems of connecting a biogas power plant on the power grid. It describes all the working process of biogas plants with detailed overview of prime movers of biogas plants and also describes their working principles. It gives information about biogas production processes and positive and negative aspects of production and usage of biogas on environment and human beings. There is also an overview of situation with biogas power plants in Croatia. The paper contains technical and legislative conditions of connection of power plants to the power grid. In this paper an example of connection of biogas power plant to HEP power grid is given. It is about Biogas Power Plant Crnac 1 with power of 670 kW. It contains analysis of observed system with DIgSILENT PowerFactory 14 software. The analysis present conditions in observed system with minimal and maximal load and it gives the effects of breakdowns on certain points in the power grid before and after connection of biogas power plant.
Parallel keywords (Croatian)bioplinska elektrana plinska elektrana plinski motori kogeneracija bioplin bioplinsko postrojenje mrežna pravila EOTRP